Zhengzhou Sinoma Engineering Technology Co., Ltd
Uzbekistan 30 t/h Coal Powder Preparation — LM190 Vertical Roller Mill - Zhengzhou Sinoma Case
Project Case

Uzbekistan 30 t/h Coal Powder Preparation — LM190 Vertical Roller Mill

LM190 vertical roller mill for 30 t/h coal powder preparation at a cement plant in Uzbekistan. EPC coal grinding system with 25% energy saving vs ball mill. Contact Zhengzhou Sinoma.

Capacity 30 t/h
Location Uzbekistan
Delivery Time 2023-06-15
Contact Us Online
Fast Response
100+ Countries
30 Years Exp

Project Details

Project Overview

This 30 t/h coal powder preparation line was built for a large cement group in Uzbekistan, using our LM190 vertical roller mill (VRM) as the core grinding equipment. The plant prepares pulverized coal (PC) for the group's cement kiln, replacing an old ball mill circuit that had become energy-intensive and unreliable.

The customer selected Zhengzhou Sinoma Engineering Technology as the EPC contractor after comparing four Chinese and European vertical mill suppliers. The contract covered process design, equipment manufacturing, sea logistics, on-site installation supervision, commissioning, and operator training — delivered as a single-turnkey package.

Why the Customer Chose a Vertical Roller Mill Over a Ball Mill

The old coal grinding system used two ball mills in closed circuit. By the end of 2021, the group had three pain points:

  • High specific power consumption — ball mill system drew over 32 kWh/t at 80 μm fineness

  • Unstable fineness — screen blocking caused R90 to swing between 8% and 15%, hurting kiln combustion stability

  • High maintenance frequency — ball mill liners and media required replacement every 8–10 months

A vertical roller mill was chosen because it integrates grinding, drying, and classification in one machine, typically cutting specific power consumption by 20–30% versus a ball mill circuit.

Technical Configuration

The line is a closed-circuit VRM system with the following key parameters:

ItemSpecification
Core millLM190 vertical roller mill × 1
Raw materialBituminous coal / lignite blend
Feed size≤ 35 mm
MoistureUp to 12% (dried in-mill with kiln exhaust gas)
Output30 t/h
Product finenessR0.08 = 5–10% (adjustable)
Main motor power800 kW
System power consumption~26 kWh/t (at R90 = 8%)
Dust collectionPulse bag filter, outlet < 10 mg/Nm³

Auxiliary equipment supplied:

  • Coal feeder and rotary airlock

  • High-efficiency dynamic separator

  • Induced draft fan and stack

  • Explosion-protected bag filter (CO monitoring + extinguishing)

  • DCS control system with touchscreen HMI

Project Implementation

PhaseTimelineKey Activity
Contract signingMarch 2022Detailed engineering kickoff, site survey completed
ManufacturingApr – Nov 2022Grinding table, rollers, separator and casing fabricated in-house
ShippingDec 2022 – Feb 2023Breakbulk from Tianjin to Tashkent via IRU road + rail
InstallationMar – Jul 2023Mechanical erection, ducting, electrical and DCS integration
CommissioningAug 202330 days on-site trial run, classifier tuning, operator training
Commercial operationSep 2023Handover to client, performance guarantee test passed

The main construction challenge was the remote site location and limited local lifting capacity. Our team solved it by using modular mill assembly on site — the grinding table and rollers were pre-split in the workshop to fit a 50-ton crawler crane, cutting erection time by roughly two weeks.

Results After 12 Months of Operation

  • Capacity: Sustained 30–32 t/h, 10% above guarantee

  • Energy saving: Specific power dropped from 32 kWh/t to 26 kWh/t — about 25% reduction, saving roughly USD 1.2 million per year in electricity at local tariffs

  • Fineness stability: R0.08 held at 6–8% with standard deviation below 1%, stabilizing kiln combustion

  • Uptime: Over 8,000 running hours without major overhaul; first roller tire re-surfacing scheduled after 12,000 hours

  • Payback: Customer projects payback period under 3 years, driven mainly by power savings and reduced liner/media consumption

Customer Feedback

"The LM190 vertical mill from Zhengzhou Sinoma has transformed our coal grinding section. Power consumption dropped immediately after commissioning, and the DCS system makes fineness tuning almost automatic. Their engineer stayed until we could run the line confidently on our own. We are now discussing a second VRM for our slag grinding circuit."

Related Equipment

Interested in a similar coal powder preparation line? See our vertical roller mill and ball mill range, or contact our engineers for a tailor-made solution for your cement plant or power station.

Inquire Now

Get a Quotation

Please fill in the form below (* are required) to send us a brief message, we will reply to you within 12 hours/provide you with the latest quotes.

OR WhatsApp

SERVICE PROMISE

Senior technical engineers provide you with customized solutions and professional installation services to effectively solve your problem in after-sales.

1
Project
Design
2
Customer
Receiving
3
Contract
Signing
6
Testing
&Maintenance
5
Equipment
Installation
4
Manufacturing
&transportation